Home /

Our Projects

Major Projects

Completed Projects

Planned / On-going Projects

Provision of Study Space at Mong Man Wai Library

Conversion of existing roof area to study spaces and discussion rooms at 2/F between Blocks B4 & C, and Blocks C & D1 as an extension to the Library. Construction works will be commenced in Q2 2026 for completion tentatively in Q4 2027.

Provision of Teaching Venues at Block D

Construction of 5 numbers new teaching venues at G/F of Block D. Construction works will be commenced in Q2 2026 for completion tentatively in Q4 2026.

Improvement of Teaching Venues at Block B and Block D

Six teaching venues on the LP/F of Block B (B1-LP-03, B1-LP-06, B1-LP-07 and B2-LP-13) and Block D (D2-LP-18 and D3-LP-15) will be renovated in two phases. The renovation works are tentatively scheduled in Q3 2026 and Q1 2027 respectively.

Improvement of Teaching Venues at B2 to B4

7 numbers of classrooms at B2 to B4 LP floor will be renovated in phases. The first phase of construction works (Room B2-LP-14, 20 and 21) have been completed in Dec 2024. The second phase (Room B2-LP-22, 23 and B3-LP-08) have been commenced in Jan 2025 for completion tentatively in end Jun 2025. All phases of construction works are scheduled for completion tentatively in Q4 2025.

Improvement of Lecture Theatre C-LP-11

Renovation works of C-LP-11, which is the largest theatre on Tai Po Campus, have been commenced in December 2024 for completion tentatively in June 2025.

Improvement Works of Chan Shiu-chow Performing Studio D2-LP-05

Design for D2-LP-05 is in progress, the tender for works contract will be issued in July 2025.  Renovation works will be carried out tentatively in January 2026.

New Academic Building in Tai Po Campus

New Academic Building in Tai Po Campus, which is the first ever subvented capital works project implemented since the establishment of the campus, was approved by the Finance Committee of the Legislative Council on 15 July 2022 with the Approved Project Estimate at $651.2 million in money-of-the-day (MOD) prices. The main works of the project subsequently commenced on 29 August 2022 for completion tentatively in Q3 2025.

Improvement works of Lecture Theatres (D1-LP-02 to 04)

Renovation of D1-LP-02 and D1-LP-03 were completed in September 2023 and December 2023 respectively. The works for D1-LP-04 has been commenced in January 2024 for completion tentatively in mid-2024.

Replacement of Lift Systems at Student Hostels, Jockey Club Student Quarters and Senior Staff Quarters

The aging lifts covering high zone floors of Hall A to Hall C and all lifts of JCSQ and SSQ will be replaced in phases from 2025 to 2027. The first phase will be commenced in Aug 2025.

Improvement of Lift Systems at Hostels

All lifts (Mid zone and Low zone) have been completed on 5 March 2025.

Tseung Kwan O Study Centre Improvement Works

5 nos. of function rooms at TKOSC will be renovated in phases, the first phase of construction works (Room 205 and G05) have been completed in Dec 2024. The second phase (105 Lecture theater) have been commenced in Dec 2024 for completion tentatively in early of Jun 2025. The third phase (Room 306 and 605) have been commenced in Jun 2025 for completion tentatively in end Nov 2025. All phases of construction works are scheduled for completion by Q4 2025.

Improvement of Toilets and Resurfacing of Basketball Court at Tseung Kwan O Study Centre

The toilet facilities will be upgraded in phases from 2025 to 2026 with touchless features incorporated for hygienic consideration and other water saving sanitary fittings provided. The outdoor basketball court will also be renovated tentatively in end 2025.